On compliance of Section 313(1) and (3) of the Electricity Market Law and paragraphs 21.3, 28, 30, 31, 48.4 of and Annex 3 to the Cabinet of Ministers Regulation No 560 of 2 September 2020 ‘Regulation on the production of electricity using renewable energy sources, as well as on price determination procedures and control’ with Article 1 and the first sentence of Article 105 of the Constitution of the Republic of Latvia
Years
2021
Stages of the proceedings
Adjudicated
Outcome of the proceedings
Judgement
Type of the proceedings
Court sitting with the participation of the participants of the case
Applicant
Person
Applicant: AS „ZIEDI JP”; SIA „AD Biogāzes stacija”; SIA „BIO FUTURE”; SIA „GAS STREAM”; SIA „Conatus BIOenergy”; AS „International Investments”; SIA „Agro Iecava”; SIA „RZS ENERGO”; SIA LATVIJAS LAUKSAIMNIECĪBAS UNIVERSITĀTES MĀCĪBU UN PĒTĪJUMU SAIMNIECĪBA „VECAUCE”
Date of the judgment: 27.10.2022.
Official publication: 31.10.2022.

On compliance of Section 313(1) and (3) of the Electricity Market Law and paragraphs 21.3, 28, 30, 31, 48.4 of and Annex 3 to the Cabinet of Ministers Regulation No 560 of 2 September 2020 ‘Regulation on the production of electricity using renewable energy sources, as well as on price determination procedures and control’ with Article 1 and the first sentence of Article 105 of the Constitution of the Republic of Latvia


Press-releases